RENOVATION FINISHES & PROCUREMENT

Make the tile order follow the finish schedule.

Work from measured surfaces, then review allowance, whole boxes and the actual product.

TrendyBuilders editorial team · Reviewed 29 November 2026 · Worked examples

A renovation tile purchase should follow the rooms and surfaces in the finish schedule. A home’s total floor area does not automatically describe the area to tile. Identify changes of finish, excluded zones and the boundary between new and retained work.

Measure the actual surfaces

Record floor and wall tiling separately. Keep skirtings, trims, thresholds and other details visible rather than assuming a single area rate covers them. Confirm the drawing or site-measurement reference and the deduction basis used for each zone.

Apply the planning allowance before rounding

A rectangular 6 m × 5 m floor measures 30 m². With an illustrative 10% allowance, required coverage is 33 m². At example box coverage of 1.44 m², 33 ÷ 1.44 rounds up to 23 whole boxes. Purchased coverage is 33.12 m².

At an illustrative NZD 50 per box, the tile material subtotal is NZD 1,150. It is a worked example, not a price recommendation or supplier quotation. The allowance is also editable and must be reviewed for the actual pattern, product and cutting layout.

Confirm the selected product before ordering

Check box coverage, tile dimensions, batch, finish, pattern and spare requirements with the supplier. Record what can be supplied together and any stated lead-time or return conditions. Do not assume the demo’s packaging matches a chosen product.

Separate purchase from installation

The subtotal excludes adhesive, grout, trims, preparation, removal of existing finishes, labour, delivery and tax. If an installed quotation includes some of those items, record that scope before adding separate cost lines.

Compare the same package: use the same room schedule, specification and preparation boundary when reviewing alternative offers.

Use the tile demo to inspect the rounding, then copy reviewed quantities into the main TB platform manually. These local demo inputs are not saved or transferred automatically.

BUILD THE BASIS BEFORE THE COMMITMENT

Give your next alteration or building estimate a clear starting point.